GATE EE · Power Systems
Generate GATE-level questions on Economic Load Dispatch. Focus on: 1. Incremental fuel cost and Optimal scheduling of generation without and with losses. 2. Penalty factors and Loss coefficients. 3. Unit commitment and Hydro-thermal scheduling basics.
15 questions · 15 PYQs · 0 AI practice · GATE EE 2027
🎯 These are sample questions
Just sign in to unlock everything. Free for all students.
The incremental cost curves of two generators (Gen A and Gen B) in a plant supplying a common load are shown in the figure. If the incremental cost of supplying the common load is Rs. 7400 per MWh, then the common load in MW is ____ (rounded off to the nearest integer).

The fuel cost functions in rupees/hour for two 600 MW thermal power plants are given by where and are power generated by plant 1 and plant 2, respectively, in MW and is constant. The incremental cost of power is 8 rupees per MWh. The two thermal power plants together meet a total power demand of 550 MW. The optimal generation of plant 1 and plant 2 in MW, respectively, are
Two generators have cost functions and . Their incremental-cost characteristics are They need to deliver a combined load of . Ignoring the network losses, for economic operation, the generations and (in ) are
Two generating units rated 300 MW and 400 MW have governor speed regulation of 6% and 4% respectively from no load to full load. Both the generating units are operating in parallel to share a load of 600 MW. Assuming free governor action, the load shared by the larger unit is _______ MW.
Consider the economic dispatch problem for a power plant having two generating units. The fuel costs in Rs/MWh along with the generation limits for the two units are given below: ; ; The incremental cost (in Rs/MWh) of the power plant when it supplies 200 MW is ______ .
The incremental costs (in Rupees/MWh) of operating two generating units are functions of their respective powers in MW, and are given by where . For a certain load demand, have been chosen such that =76Rs/MWh and =68.8 Rs/MWh. If the generations are rescheduled to minimize the total cost, then is ________.
The fuel cost functions of two power plants are Plant Plant where, are the generated powers of two plants, and A and B are the constants. If the two plants optimally share 1000 MW load at incremental fuel cost of 100 Rs/MWh, the ratio of load shared by plants is
The figure shows a two-generator system applying a load of = 40MW, connected at bus 2. The fuel cost of generators G1 and G2 are : =10,000 Rs/MWh and =12,500 Rs/MWh and the loss in the line is , where the loss coefficient is specified in pu on a 100 MVA base. The most economic power generation schedule in MW is

A load center of 120 MW derives power from two power stations connected by 220 kV transmission lines of 25 km and 75 km as shown in the figure below. The three generators G1, G2 and G3 are of 100 MW capacity each and have identical fuel cost characteristics. The minimum loss generation schedule for supplying the 120 MW load is

Three generators are feeding a load of 100 MW. The details of the generators are In the event of increased load power demand, which of the following will happen ?

A loss less power system has to serve a load of 250 MW. There are tow generation (G1 and G2) in the system with cost curves respectively defined as follows: where are the MW injections from generator G1 and G2 respectively. Thus, the minimum cost dispatch will be
The incremental cost curves in Rs/MWhr for two generators supplying a common load of 700 MW are shown in the figures. The maximum and minimum generation limits are also indicated. The optimum generation schedule is :

A load centre is at an equidistant from the two thermal generating stations and as shown in the figure. The fuel cost characteristic of the generating stations are given by Where are the generation in MW of and , respectively. For most economic generation to meet 300 MW of load respectively, are

Incremental fuel costs (in some appropriate unit) for a power plant consisting of three generating units are Where is the power in MW generated by unit i for i=1,2 and 3. Assume that all the three units are operating all the time. Minimum and maximum loads on each unit are 50 MW and 300 MW respectively. If the plant is operating on economic load dispatch to supply the total power demand of 700 MW, the power generated by each unit is
Consider a power system with three identical generators. The transmission losses are negligible. One generator has a speed governor which maintains its speed constant at the rated value, while the other generators ( and ) have governors with a droop of 5%. If the load of the system is increased, then in steady state.
Want unlimited AI-generated Economic Power Generation And Load Dispatch questions?
Sign up free and practice with adaptive difficulty — Easy, Medium, Hard. New questions every session.
Start practising for free →