The point where the road alignment changes from a tangent to a curve is known as ______
Road and Road are joined by a circular horizontal curve of radius 200 m as shown in the figure. Road and Road are tangential to the curve at the points and , respectively. Had the curve not been there, straight roads and would have met at the point . The distance from to is 92 m . The value of angle (in degrees) is ________ (rounded off to 1 decimal place). Note: The value of angle is to be calculated only from the consideration of Euclidean geometry and the data given in the problem.

On a two-lane highway, a horizontal curve of radius is provided. The design speed is . If the longest wheelbase of the vehicle expected on this highway is , then the extra widening required (in m) is ______ (round off to two decimal places).
A vertical summit curve on a freight corridor is formed at the intersection of two gradients, and . Assume the following: Only large-sized trucks are allowed on this corridor. Design speed Eye height of truck drivers above the road surface Height of object above the road surface for which trucks need to stop Total reaction time of the truck drivers Coefficient of longitudinal friction of the road Stopping sight distance gets compesnated on the gradient. The design length of the summit curve (in meters) to accommodate the stopping sight distance is _____ (rounded off to 2 decimal places).
A car is travelling at a speed of on a section of a National Highway having a downward gradient of . The driver of the car suddenly observes a stopped vehicle on the car path at a distance ahead, and applies brake. If the brake efficiency is , coefficient of friction is 0.7 , driver's reaction time is . and acceleration due to gravity is , the distance (in meters) required by the driver to bring the car to a safe stop lies in the range
In general, the outer edge is raised above the inner edge in horizontal curves for
and are the slopes of the approach and departure grades of a vertical curve, respectively. Given and Statement 1: followed by results in a sag vertical curve. Statement 2: followed by results in a sag vertical curve. Statement 3: followed by results in a crest vertical curve. Which option amongst the following is true?
For a horizontal curve, the radius of a circular curve is obtained as with the design speed as . If the allowable jerk is , what is the minimum length (in , in integer) of the transition curve ?
Which of the following is equal to the stopping sight distance?
As per the Indian Roads Congress guidelines (IRC 86: 2018), extra widening depends on which of the following parameters?
A parabolic vertical crest curve connects two road segments with grades +1.0% and -2.0%. If a 200 m stopping sight distance is needed for a driver at a height of 1.2 m to avoid an obstacle of height 0.15 m, then the minimum curve length should be ______ m. (round off to the nearest integer)
The vehicle count obtained in every 10 minute interval of a traffic volume survey done in peak one hour is given below.
The peak hour factor (PHF) for 10 minute sub-interval is __________. (round off to one decimal place)
The base length of the runway at the mean sea level (MSL) is 1500 m. If the runway is located at an altitude of 300 m above the MSL, the actual length (in m) of the runway to be provided is ____________. (round off to the nearest integer)
A horizontal curve is to be designed in a region with limited space. Which of the following measure(s) can be used to decrease the radius of curvature?
The stopping sight distance (SSD) for a level highway is 140 m for the design speed of 90 km/h. The acceleration due to gravity and deceleration rate are and , respectively. The perception/reaction time (in s,round off to two decimal places) used in the SSD calculation is ______________
The shape of the most commonly designed highway vertical curve is
On a road, the speed - density relationship of a traffic stream is given by u=70 - 0.7k (where speed, u, is in km/h and density, k is in veh/km). At the capacity condition, the average time headway will be
A highway designed for 80 km/h speed has a horizontal curve section with radius 250 m. If the design lateral friction is assumed to develop fully, the required super elevation is
The design speed of a two-lane two-way road is 60 km/h and the longitudinal coefficient of friction is 0.36. The reaction time of a driver is 2.5 seconds. Consider acceleration due to gravity as 9.8 . The intermediate sight distance (in m, round off to the nearest integer) required for the load is ________
In an urban area, a median is provided to separate the opposing streams of traffic. As per IRC : 86-1983, the desirable minimum width (in m, expressed as integer) of the median, is __________.