The Job Sequencing with Deadlines problem aims to maximize profit by scheduling unit-time jobs before their deadlines. Given jobs: J1(profit=100, deadline=2), J2(profit=10, deadline=1), J3(profit=15, deadline=2), J4(profit=27, deadline=1). The greedy strategy selects jobs in decreasing order of profit. What is the maximum profit achievable?